Quamby

Project Name: Quamby Irrigation Intake Upgrades

Client: Tasmanian Irrigation

Location: Deloraine, Tasmania

Timeline: Q2-Q3 2023

Overview: This project is right up there as one of the best examples of what Sub41 can deliver for clients using our years of offshore experience and applying it to local projects here in Tasmania. Steering away from conventional cofferdam solutions due to water depth and flood exposure, Sub41 went underwater using pre-made templates, underwater grouting and pre-installed fixtures. Going bigger on the engineering and pre-works resulted in a project that typically takes 5-6 months being completed within 5 weeks onsite and only 1 day or weather downtime.  A new record by a considerable margin for this client and the landowner who always are a major consideration when working on private land.    