Shutdown Support for CEMAST
James and Ben planned and supervised the clinker hall refurbishment project coving 24hrs during the 2024 kiln shutdown. Crisp Bros - Haywards were the primary subcontractor for the works and the project was completed a week ahead of schedule and well under budget. The tower which has been in continual service for 38years had windows, sills and hard facing inspected and repaired; tower legs sleeved, chutes lined and concrete repairs, discharge gates rebuilt and the 200T reclaimer system cut up and removed.